Progress on recovery at Kingwood High School continues and things are looking great, according to Humble ISD. The goal is for students to be back in the academic wing March 19. The following update is of Dec. 12: brick veneer installation is completed in the main corridor; insulation, fireproofing and drywall is 99 percent complete throughout the entire campus; painting is complete through 90 percent of the entire building, including the girls fieldhouse; ceramic tile is complete in the 2000 area restrooms, kitchen and cafeteria; tile on floors and walls of the kitchen is complete; carpet is 50 percent complete in the 2000 wing classrooms; restoration continues in the fine arts wing, athletics area and CTE hallway; painting is complete in the natatorium, practice gym and the competition gym; IT data cabling and systems are being restored and brought back online; all sewer lines and sanitary sewers are being jetted and hydrovacuumed to remove flood sediment; and new plumbing fixtures such as drinking fountains, lavatories and water closets are being installed.